Oncor Electric Delivery intelligence

Landowners and lawmakers continue to speak out against Oncor’s proposed line as they await a decision

Part of: Oncor's 765-kV plan faces widening scrutiny · See the full timeline

October 05, 2026 · Updated October 06, 2026 · Curated by 247ignite
Critical

Top StoryLandowners and lawmakers continue to speak out against Oncor’s proposed line as they await a decision

kwtx.com

The Texas Public Utility Commission (PUC) has sent Oncor's proposed 765kV Big Hill transmission line project back to administrative law judges for additional review. The project, which would span nearly 200 miles across Central and West Texas, has encountered significant opposition from landowners and lawmakers. Concerns include insufficient demonstrated need and inadequate notification to 1,400 affected individuals. The PUC has requested further analysis on compliance with federal and state reliability standards as well as congestion cost savings.

In August, administrative law judges recommended against approval, citing similar concerns. The timeline for a final decision remains uncertain, while landowner challenges and additional filings with the PUC continue to add pressure.

Why it matters: This delay prolongs uncertainty for a critical infrastructure project aimed at improving grid reliability and reducing congestion costs in Texas, particularly in the high-demand Permian Basin. It also highlights the broader regulatory and stakeholder challenges facing large-scale energy projects in the state.

Track Oncor Electric Delivery yourself, free

Get a daily briefing tailored to your role, tracking Oncor Electric Delivery and any company or market you choose.

Create my Oncor Electric Delivery briefing →